Untapped capacity from existing equipment
—
—
Current OEE —
Target —
More sales, same equipment
—
—
Same sales, lower cost
—
—
Note – this is one or the other, not both
Where the capacity is sitting
—
How to interpret and use the results
- This line has to be the constraint. Recovered capacity on a line that is not the bottleneck produces inventory, not revenue.
- Hours and availability must be on the same basis. Availability is runtime ÷ scheduled time, so the hours entered have to be that same scheduled time. Exclude hours the line was never scheduled to run — holidays, unstaffed shifts, planned shutdowns. Keep changeovers, breakdowns and material outages in; those are availability losses, not schedule reductions.
- The ideal rate has to be a ceiling. If the line routinely beats its design rate, use the best rate you have sustained under normal product mix instead. A reference the line regularly beats and a one-off record on your easiest product both overstate the opportunity.
- Use measured OEE, not estimated. If availability comes from a supervisor's impression rather than downtime records, the answer is a guess.
- Contribution margin, not price. Extra units carry variable cost. Using the selling price can overstate the value by several times.
- Cost savings are only real if the hours actually come out. Saved hours become real money when a shift is dropped or overtime is cut. If the crew stays on the clock while the line sits idle, the hours were shifted, not saved.
- The demand has to exist. Capacity is only worth something if there is volume to put through it, or a cost to take out of it.
- 85% OEE is a benchmark, not a target. What matters is the gap between your line and its own best sustained performance.