OEE Capacity Calculator
What is your equipment already capable of?

Before you buy a line, find out how much capacity you are leaving on the table. Enter your current equipment performance information and see what a realistic OEE improvement is worth in units and dollars.

Your line

What you want from the capacity

Sell more from the same equipment. Recovered capacity becomes additional units at your contribution margin.

Operating pattern

Scheduled production time: 4,000 hours per year

Use the same basis as your Availability figure. Leave out hours the line was never scheduled to run; keep changeovers and breakdowns in. Not sure? Assume scheduled production time — that is how most plants report it.

Rate and value
Current OEE
Total OEE— —
Target

Untapped capacity from existing equipment

—

—

Current OEE — Target —

More sales, same equipment

—

—

Same sales, lower cost

—

—

Note – this is one or the other, not both

Where the capacity is sitting

—

How to interpret and use the results

  • This line has to be the constraint. Recovered capacity on a line that is not the bottleneck produces inventory, not revenue.
  • Hours and availability must be on the same basis. Availability is runtime ÷ scheduled time, so the hours entered have to be that same scheduled time. Exclude hours the line was never scheduled to run — holidays, unstaffed shifts, planned shutdowns. Keep changeovers, breakdowns and material outages in; those are availability losses, not schedule reductions.
  • The ideal rate has to be a ceiling. If the line routinely beats its design rate, use the best rate you have sustained under normal product mix instead. A reference the line regularly beats and a one-off record on your easiest product both overstate the opportunity.
  • Use measured OEE, not estimated. If availability comes from a supervisor's impression rather than downtime records, the answer is a guess.
  • Contribution margin, not price. Extra units carry variable cost. Using the selling price can overstate the value by several times.
  • Cost savings are only real if the hours actually come out. Saved hours become real money when a shift is dropped or overtime is cut. If the crew stays on the clock while the line sits idle, the hours were shifted, not saved.
  • The demand has to exist. Capacity is only worth something if there is volume to put through it, or a cost to take out of it.
  • 85% OEE is a benchmark, not a target. What matters is the gap between your line and its own best sustained performance.